Completed Projects


Project : Construction of Yanqul - Fida - Dank Road
Client : Ministry of Transport and Communication; Directorate General of Road and Land Transport
Consultant : Parsons International and Company LLC
Cost : OMR 23,323,754.000
Duration : 30 Months
Scope : The project includes construction of two lane carriageway of 12m width from Yanqul to Dank, including the construction of 17 R C Box Culverts, 8 Irish Crossings and Protection works. The Carriageway consists of both Flexible and Rigid Pavem ents. The maj or length of the road is of Concrete Pavement.